In this issue, we discuss how recommissioning projects can optimize your buildingโ€™s overall energy performance. We also highlight how HSC is working to ensure our sector is supported in undertaking energy and emissions reduction projects, and we remind our Utility Management Program users to log-in to see their utility performance since last quarter. Enjoy!

In this issue:


Time for a Tune-up? Building Commissioning Can Optimize Performance

Undertaking an Existing Building Commissioning (EBCx) project can achieve energy savings of up to twenty percent in your buildings. EBCx is a process that focuses on optimizing or โ€œtuning upโ€ your existing equipment and systems and making low or no-cost operational improvements.

Beyond savings, an EBCx project can lead to improved resident comfort, longer equipment life, improved indoor air quality, and lower greenhouse gas emissions in your properties.

What is EBCx?
Generally, EBCx involves verifying and documenting all systems, equipment, and their operations and maintenance (O&M) to ensure a facilityโ€™s current requirements are met. Building operators can then identify measures to improve or optimize performance, after which they document and monitor the performance of implemented measures and train staff on proper O&M procedures.

EBCx includes:

  • Recommissioning (RCx) of previously commissioned equipment to re-optimize its operation,
  • Retro-commissioning of existing equipment that wasnโ€™t previously commissioned, and
  • Ongoing commissioning (OCx) of new equipment as it is installed. Existing systems may need to be recommissioned to address O&M changes resulting from the new installations.

Source: Natural Resources Canada

What are the benefits?

Recommissioning is normally done every three to five years depending on how well O&M procedures have been followed and any changes in building use. While this may seem frequent, there are many benefits to recommissioning:

  • Lower utility use by 5 to 15%;
  • Lower operating expenses;
  • Improved indoor environmental quality with positive health and comfort impacts for residents and increased protection from liability claims; and
  • Lower repair and replacement costs since recommissioning helps extend equipment life and reduce the need for repairs.

What does recommissioning cost?

Because recommissioning can be different for each building, the costs of each project are unique to the project itself. Key variables to consider are:

  • Scope of the project
  • Number and complexity of systems
  • Building size
  • Equipment age and condition
  • Commissioning service provider’s costs
  • Amount of knowledge of building staff assigned to the project
  • Completeness and relevance of existing O&M programs and documentation

The Independent Electricity System Operator (IESO) has incentives for recommissioning on larger buildings and portfolios. It may be worth contacting the IESO to see if your building is eligible.

Your own staff can help you save costs on a recommissioning project by collecting documentation, identifying existing problem areas, and performing planned maintenance prior to the start of the recommissioning project.

While itโ€™s important to understand the cost of recommissioning, itโ€™s even more important to ask the cost of not undertaking recommissioning. Resident complaints, work orders, high energy use, and equipment repair and replacement costs can add up if not addressed through recommissioning.

Where Do You Start?
Natural Resources Canada has a webpage with information, tools, and case studies about EBCx projects to help you get started. In particular, check out Natural Resources Canadaโ€™s Recommissioning Guide for Building Owners and Managers for helpful steps to undertake recommissioning projects. You may also use the Existing Building Commissioning Pre-Screening Tool to help you identify the best building candidates.

Consider recommissioning or retro-commissioning your buildingโ€™s equipment and systems to ensure they are operating optimally and functioning properly together. The benefits of these projects are well worth the effort.

This article is based on content summarized from Natural Resources Canada’s Recommissioning Guide and webpage.


Getting the (Energy) Word Out on Community Housing

Wondering what HSCโ€™s Energy Services team does throughout the year? In addition to delivering our AssetPlanner, Natural Gas Purchasing, and Utility Management programs, our team works hard to engage with government and utilities about our sectorโ€™s capital renewal needs and interest in energy efficiency and emissions reduction.

Check out the conversations we are having to help the sector. So far this year, we:

  • Provided face-to-face connectivity between Ontario Housing Providers, government and utilities at this year’s Regeneration Forum
  • Continued to intervene on behalf of the sector on Ontario Energy Boardโ€™s consultations on Enbridge Gas energy efficiency incentive programs for the 2026-2030 period. We also regularly meet directly with Enbridge Gasโ€™ Income Qualified team to ensure the sectorโ€™s interests are considered in their programs and that housing providers can readily access program information.
  • Presented an overview on the history and structure of community housing to the Independent Electricity System Operator (IESO) to help clarify the challenges and opportunities for delivering energy efficiency incentive programs to our sector.
  • Participated in the City of Torontoโ€™s focus group on whether to make reported energy and water usage data public without anonymizing building owners under the Cityโ€™s energy and water reporting and benchmarking by-law.
  • Met with several housing providers to understand their shared questions about electricity pricing and provided helpful insights into recent rates.
  • Met with the Province of Manitoba to share our experiences supporting Ontario housing providers in undertaking building condition assessments and using capital planning software in their capital renewal activities.
  • Held several one-on-one meetings with clients in our HSC Natural Gas Purchasing Program to discuss the current market and available rate options.
  • Coordinated two consultations this June for the IESO and Enbridge Gas to gather input from Service Managers, District Social Services Administration Boards, and housing providers on the future design and delivery of energy efficiency incentive programs.
  • Engaged the Housing, Infrastructure and Communities Canadaโ€™s Climate Toolkit and Solutions Office to understand their capacity building programs and discuss ways to support Ontario community housing in undertaking energy efficiency and emissions reduction projects.

With the first half of 2025 under our belts, we look forward to building on these conversations over the rest of the year as we work to support the sector in its energy efficiency and emissions reduction activities.


Track Your Utilities with HSC’s Utility Management Program (UMP)

How do you know if your utility use is increasing or decreasing when weather changes year to year? How can you tell if any energy and water saving projects are having an impact? HSCโ€™s Utility Management Program (UMP) accounts for differences in weather each year so you can view an apples-to-apples comparison of your building utility performance over time and from one year to the next.